(Hpa-an)
2012
Hpa-an
8 months
Waste heat recovery power generating system. Large and small-bore piping.
(Myin Gyan)
2008
No.1 Steel Mill(Myan Gyan)
2 months
A mile long PE pipe installation.
(MWDC, Hlegu)
2005
Hlegu
6 months
Piping Installation and Machine Installation.
(Hpa-an)
2000
Hpa-an
1 and a half month
Pipelines installation for carrying and treating water from Thanlyin River to the cement factory in Myaing Kalay.
(Hpa-an)
2000
Hpa-an
1 month
The height of 90 m with Japanese design. Both fabrication and installation. Internal air piping.